Paving Projects

On September 18, 2023, the Board of Mayor and Aldermen (BOMA) voted to approve a list of paving projects for Fiscal Year 2024.

Rogers Group was selected to carry out the paving projects across the city. With a 10% contingency included, the total cost was estimated at $2,708,629.28, which is being paid for with $708,629.28 from the State Street Aid Fund and $2 million from the General Fund.

The following neighborhoods will be included in this round of repaving:

  • Picketts Ridge
  • Haynes Crossings 
  • Wyngate
  • Cameron Farms 
  • Cochran Trace
  • Hurt Road
  • Burtonwood
  • Candlewood
  • Belshire
  • Baker Springs

paving maps for neighborhoods_Page_01

These areas were identified as a result of an annual assessment by Spring Hill Public Works, examining all roads in the city:

paving pdf

The streets chosen for repaving fall under the very poor and/or poor category.

Any remaining funds from these projects will be used for miscellaneous paving projects that need to be repaired throughout FY 2024.