Duplex Road utility relocation underway in preparation for widening

Duplex Road Utility Relocation

As the City of Spring Hill’s $3.5 million acquisition of 210 properties for road right-of-way is wrapping up on Duplex Road, the relocation of utilities is now underway in preparation for TDOT’s widening of Duplex Road (S.R. 247).

Utilities, both above and underground, must be moved to the edges of the expanded right-of-way path by each of the respective utility companies (including Middle Tennessee Electric, Columbia Power, City of Spring Hill Water and Sewer, Atmos Energy natural gas, Charter Communications, and AT&T).

Additional, temporary wooden power poles are being placed alongside existing poles to transfer power lines in preparation for the road expansion. Permanent metal poles will be installed later.

“We are pleased to see the utility relocation phase progressing in advance of the actual road construction phase to help eliminate utility conflicts that will allow road construction work to progress efficiently,” Assistant City Administrator Chuck Downham said. “With so many utilities affected by this road project, we appreciate the cooperation and coordination that is being provided by all the utility providers as the utility relocation process continues to move forward.”

The relocation of utilities is being funded by the City of Spring Hill at an additional cost of about $3.5 million, while the coordinating of each of the utility companies and management of the relocation project is being handled by TDOT.

TDOT will fund the $17.3 million construction of the widening, currently anticipated for bid letting later this summer.

The total $22.25 million project will widen the full 3.1-mile stretch of Duplex Road to three lanes (two travel lanes and a center turn lane) from U.S. 31 (Main Street) to I-65, complete with curb and gutter, a sidewalk on the south side of the road and a multi-use path on the north side. The sidewalk and multi-use path will each be separated from the roadway by a narrow grass median.

The project includes installation of four new traffic signals on Duplex, two of which have already been installed by the City at Port Royal Road and Miles Johnson Parkway. The other two signals will be installed at Buckner Lane and Commonwealth Drive. The project also will greatly improve vertical and horizontal alignment by cutting down taller blind hills and aligning the roadway for better visibility.

Additional Info...
Facebook Twitter Google Plus Email

Other News in Home

Spring Hill Farmers Market

Spring Hill Farmers Market

Posted on: April 7, 2017
PSA Please don't litter. Help keep Spring Hill clean

Help us keep Spring Hill clean!

Posted on: February 1, 2017
Burn Ban Lifted

Countywide burn ban lifted

Posted on: December 9, 2016
Exxon robbery suspects

Suspects sought in Exxon robbery

Posted on: October 17, 2016

State of the City Address, Jan. 28

Posted on: January 24, 2016
Christmas Tree Recycling

How to dispose of your Christmas tree

Posted on: January 4, 2016
2015 in review

2015 another big year for Spring Hill!

Posted on: January 4, 2016
McLemore Park

Split-rail fence completes McLemore Park

Posted on: December 7, 2015
Bank robbery suspect

SHPD tracking bank robbery suspect

Posted on: November 5, 2015
Grey Ghost 5k

Grey Ghost 5K Run road closure notice

Posted on: October 1, 2015

Don't forget to vote April 9

Posted on: April 7, 2015

Street sweeping postponed until March 2

Posted on: February 18, 2015

Spring Hill Mayor's Ball this Saturday

Posted on: November 6, 2014

Board of Mayor and Aldermen meets tonight

Posted on: September 15, 2014